Wednesday, August 29, 2007

Kramer Place is taking shape!!

The construction fences have come down and the building is really looking good! The Kramer Place Superintendent has reported the following status on construction progess.

  • Building exterior caulking is complete
  • Drywall hung on all 2nd floor unit walls & ceilings
  • Exterior lighting is on the building and the pole lights in the rear are installed and on
  • Rough plumbing, electrical and mechanical systems are complete
  • Building sprinkler system is complete and waiting for final test
  • All concrete work is complete
  • Asphalt paving is scheduled for the 2nd week in September
  • Irrigation system being installed late this week or early next week
  • Landscaping to be installed next week
  • Permanent fencing at the south end of the site will be installed 2nd week in September
  • With the exception of the 2nd & 3rd floor balconies and painting, the exterior of the building is complete

Check back for updated construction photos later this week!!

Monday, August 27, 2007

Tuesday, August 21, 2007

Tuesday, August 7, 2007

Kramer Place exterior is complete!

"As of Thursday, August 2nd, the exterior of the building is complete except for the caulking and the balcony painting. All of the balcony rails & garage security grilles are in. The roof is complete except for a little more flashing & caps. As this project continues to shape up, stay tuned for other 'building completion' updates."